Adman were appointed by Killala Community Wind Farm Ltd as Principal Contractor to undertake all Civil Balance of Plant works for Killala Wind Farm wind farm which is located in Co. Mayo.
The scope of works for the project involved the design and construct of 5 no. 2.3MW Siemens WTG with all associated infrastructure including access tracks, crane hardstands, associated drainage works and a fenced substation compound with a single storey 38kV control building/switch house. Key features of the works are as follows:
- Construction of foundations for 5 no. 2.3MW Siemens WTG’s.
- Construction of 2,400m of new 4m wide site tracks.
- Construction of substation building.
- 2500m of Cable Trenching including excavation, backfill with marker tape, compaction of suitable fill material, top soiling and grass seeding.
- 5 no. 1200m2 crane pads.
- Upgrade to public highways.
- Water Quality monitoring and testing.
- 1 number anemometer mast, foundation, access track and hard standing.