As part of Translink’s ongoing inspection and examination regime, in 2024 7no culverts were identified within the Culvert Strengthening Programme as requiring full replacement. Adman successfully delivered the first phase of this contract during a 52hr blockade starting Friday 19th April. Working across three sites simultaneously at Aughalish, Carrowdoon & Windyhall our teams successfully removed and constructed the permanent works on programme. All sites were reinstated for the first train on Easter Sunday morning with a 50MPH TSR implemented whilst track monitoring was ongoing for a seven-day period. Following seven days around the clock monitoring across all three sites, the TSR was removed and full line speed reinstated on 27th April as planned.
Already the planning has started for the second phase of the project with another four culverts being replaced over two blockades in September 2025.